Conditions for approval of evacuation and construction

Conditions for approval of evacuation and construction


For the purpose of approving the plan as a construction evacuation plan, the following conditions exist:

The number of units vacating the building evacuation area will not be less than 24 units. The complex may include a number of buildings which in general will not be less than 24 units.
The area in which evacuation is planned is located within the municipal boundaries of the municipality and the local council.
The following documents will be attached to the request for the evacuation of construction:
3.1. Initial planning for the evacuation of 24 housing units and the construction of at least 24 residential units.
3.2. The map is approved by a certified surveyor, which specifies the conditions of the area at the time of the request. The request must include details of plots and units in land.
3.3. Approval of the city engineer in whose area the land is located and the consent of the municipality to carry out a construction evacuation transaction in accordance with the planning.

Q & A on Construction Evacuation in the "Designers" Program: